Gumti Bridge Area, Cumilla, Bangladesh
As part of the larger initiative to construct the 2nd Kanchpur, Meghna, and Gumti Bridges and rehabilitate the existing ones, this project involved the establishment of temporary infrastructure to support ongoing construction. The scope included the construction of a temporary jetty and a yard at the Gumti Bridge site to facilitate the transport, storage, and staging of materials, equipment, and personnel. These support structures played a crucial role in ensuring efficient and uninterrupted progress on the main bridge works.
ROADS & HIGHWAYS DEPARTMENT OSJI JV.
Gumti Bridge Area, Cumilla, Bangladesh
completed
April 2016
August 2016
Construction
100.10 Million BDT